- A GPU render farm is a set of render nodes, a queue manager that hands out frames and shared storage for scenes and output; the node count follows from frames × minutes per frame ÷ the hours before the deadline
- Maxon's support article states that "Redshift uses a per-machine licensing model": one licence per physical or virtual computer, whatever the GPU count, and one Redshift instance uses up to 8 GPUs at a time
- OTOY's subscription page states that "OctaneStudio+ includes ten render node licenses", with no limit on GPUs, and that these node licences "are not compatible with render management software such as Deadline or TeamRender"
- AWS Thinkbox put Deadline 10 into maintenance mode on 7 November 2025, with security updates and critical fixes only; Blender's Flamenco is GPL 3.0 and in active development as version 3
- Four RTX PRO 6000 Server Edition cards draw 2,400 W and eight RTX PRO 4500 Server Edition cards 1,320 W by our arithmetic; scene memory per card decides between them (96 GB or 32 GB)
Supplied by Eurokommerz: NVIDIA RTX PRO 6000 Blackwell Request a price →
What a GPU render farm consists of
A GPU render farm is several GPU render nodes, a queue manager that splits jobs into frames or tasks and sends them to free nodes, and shared storage from which every node reads the scene and to which it writes the frames. How many nodes you need follows from three numbers: frames per job, minutes per frame on one node and the hours left before the deadline. What each node costs to run in software depends on the renderer: Maxon licenses Redshift per machine, OTOY's Octane Studio+ includes ten render node licences, Chaos sells V-Ray render node licences, and Blender Cycles needs none.
This guide starts where our article on a single GPU render server with the RTX PRO 6000 ends. That article covers renderer support, scene memory per card, multi-GPU scaling and benchmarks; here the subject is the step from one render server to several.
We supply render nodes with four or eight RTX PRO 6000 Server Edition cards or with RTX PRO 4500 Server Edition cards in servers from Supermicro, ASUS, Gigabyte, HPE and Lenovo per project. Send us your renderer, frames per week and the peak memory of your heaviest scene, and we reply with a node count and a configuration.
Render node licences: Redshift, Octane, V-Ray and Cycles
Software licences often decide the node layout before the hardware does, because some vendors count machines and others count nothing at all.
| RENDERER | LICENCE UNIT | GPUS PER LICENCE | FARM NOTE |
|---|---|---|---|
| Maxon Redshift | per machine, physical or virtual | one instance uses up to 8 GPUs | Team Render Client brings no Redshift GPU licence |
| OTOY Octane Studio+ | subscription with ten render node licences, more on request | no limit | node licences not compatible with Deadline or TeamRender |
| Chaos V-Ray | render node licence | 4 GPUs officially supported | Chaos lists Deadline, Qube and Backburner |
| Blender Cycles | GPL, no node licence | no limit | any queue manager |
Maxon support article on Redshift GPU and CPU licences for workstations and render farm nodes ("Updated", no date shown), OTOY help article "OctaneRender Subscriptions" (no date), Chaos V-Ray render node page (© 2026), all read 27 November 2026; V-Ray GPU limit and Cycles licence as cited in our GPU render server guide.
Maxon's article is the clearest of the three. "Redshift uses a per-machine licensing model", so a node with eight GPUs needs one licence, the same as a node with one. A single instance "will only use 8 of them simultaneously", and Maxon describes running several jobs on one licensed machine with the GPUs split between them, which needs a lot of system memory. "Cinema 4D's Team Render Client does not include a Redshift GPU license for the render nodes." Redshift CPU is included with the Team Render Client and the Commandline Renderer, but GPU rendering on those nodes needs a separate GPU licence. The Cinema 4D subscription includes one Redshift GPU licence for the primary workstation, which can move between machines but not run on two at once.
OTOY's current tiers are Studio+, Prime, the Render Node Subscription, Enterprise, Enterprise+ and perpetual licences with maintenance; the page summarises Enterprise, Enterprise+ and perpetual as discontinued and replaced by Studio+. For Studio+ it states: "There are no limitations to the number of GPU you can use and the license supports network rendering." The catch for a farm is the queue: "Please note these render node licenses are not compatible with render management software such as Deadline or TeamRender." An Octane farm on Studio+ node licences therefore runs on OTOY's own network rendering, and Deadline cannot drive it. The page gives no GPU limit for Prime.
Chaos's render node page says that "Render node licenses support a wide range of Chaos® V-Ray® applications", that distributed rendering can "Distribute a single render job within a single frame across many computers in a network", and that V-Ray is "Supported by popular render managers Thinkbox Deadline, PipelineFX Qube and Autodesk Backburner". It does not state whether a node licence counts per machine or per GPU, or which plans include node licences, so ask Chaos for the terms of your subscription. As our render server guide cites from a Chaos support article, V-Ray GPU officially supports a maximum of four GPUs per machine. Cycles is under the GPL and needs no node licence, and the Unreal Engine path tracer uses one card per process on cards without NVLink.
Queue managers: Deadline 10, Flamenco and others
AWS Thinkbox Deadline 10 is the queue manager that both the Chaos and the OTOY pages name, and its status changed in 2025. As CGPress reported on 6 November 2025, quoting AWS Thinkbox, Deadline 10 "will enter maintenance mode on November 7, 2025", and "active development will shift to security updates and critical fixes rather than new feature additions". The same statement says that "All existing workflows, scripts, and configurations will function as before, with no immediate action required", and that AWS Portal, the Spot Event Plugin and the Render Farm Deployment Kit "will remain fully supported".
AWS's Deadline page, updated on 17 November 2026, adds two points on licensing: "The Usage-Based Licensing (UBL) feature in Deadline 10 is now available through Deadline Cloud UBL", and "The Thinkbox UBL Marketplace will no longer function." The page promotes AWS Deadline Cloud. We found no current AWS text on the licence terms for a new on-premises Deadline 10 installation, so a new farm on Deadline 10 starts with a question to AWS.
Blender's Flamenco is the open alternative for Blender pipelines. Its site states: "Released under GPL 3.0, every component of Flamenco is Free and Open Source software." Flamenco v3 "is in active development at Blender Studio", runs on all major operating systems and defines job types in JavaScript. OpenCue, Qube and Royal Render exist as well; we have not read their current documents for this guide.
How many render nodes: frames, minutes per frame, deadline
Node count is arithmetic, once you have one measured number: the minutes per frame on the node type you plan, rendered with your own scene. A frame from the current workstation can be converted. If a test frame takes T minutes on one card, a four-card V-Ray node renders it in about T ÷ 3.9 by our arithmetic from the average scaling of 97 % with four GPUs that Chaos published and our render server guide cites.
- Count the frames per job: duration in seconds × frames per second, or the number of stills.
- Multiply by minutes per frame on one node and divide by 60 to get node-hours.
- Divide by the hours the farm may render before the deadline, round up and add a reserve for re-renders.
For an architecture studio, by our example values: a 90-second walkthrough at 25 frames per second is 2,250 frames. At 4 minutes per frame on a four-card node that is 9,000 minutes, or 150 node-hours. Rendered from Friday 18:00 to Monday 06:00, a window of 60 hours, the job needs 2.5 nodes, so three; with a 20 % reserve for corrections it is 180 node-hours, which three nodes still cover.
For a product-visualisation team, again with example values: 400 stills a week at 12 minutes each on one node are 4,800 minutes, or 80 node-hours. Five nights of 12 hours give 60 hours per node, so the team needs two nodes for night rendering only, or one node that also renders through the weekend (120 hours). Stills spread well over many small nodes, because each still is a job of its own.
Four RTX PRO 6000 Server Edition or eight RTX PRO 4500 Server Edition per node
The choice between a node with four large cards and a node with eight small ones starts with scene memory. Every card holds the whole scene, and memory does not add up across cards, as our render server guide shows from the Blender, Chaos and OTOY documents. The RTX PRO 6000 Server Edition has 96 GB and the RTX PRO 4500 Server Edition 32 GB, so scenes above 32 GB go to the large card or out of core at lower speed.
| NODE | SCENE PER CARD | CARD POWER | CPU, RAM (CHAOS) | LICENCE FIT |
|---|---|---|---|---|
| 4 × RTX PRO 6000 SE | 96 GB | 2,400 W | 24 cores, 768 GB | within V-Ray's 4 GPUs |
| 8 × RTX PRO 4500 SE | 32 GB | 1,320 W | 48 cores, 512 GB | Redshift's 8 GPUs; above V-Ray's 4 |
card memory and power from NVIDIA's figures as listed in our canon (RTX PRO 6000 Server Edition up to 600 W, RTX PRO 4500 Server Edition 165 W); 6 physical cores per GPU and system memory of twice the GPU memory as Chaos recommends, cited in our GPU render server guide; totals are our arithmetic. SE: Server Edition.
Per-card speed is known for the large card only. Blender Open Data, as our render server guide reads it for Blender 4.5.0 with OptiX, gives a median of 15,519 for the RTX PRO 6000 Server Edition and 8,487 for the RTX PRO 4500 listed without the Server Edition suffix; the table has no Server Edition row for that card. Whether eight small cards render a frame faster than four large ones therefore has to be measured with your scene; no published figure answers it.
The licence model tilts the choice further. With Redshift, eight GPUs in one machine take one licence, and Maxon's split of one machine into several jobs suits a farm of many small stills. With V-Ray GPU, an eight-card node is outside the four GPUs Chaos supports officially, so four cards per node is the safer layout. With Octane Studio+ and Cycles, the GPU count per node does not change the licence at all.
For four RTX PRO 6000 Server Edition cards, Supermicro's RTX PRO 6000 systems page lists models such as the 2U SYS-212GB-FNR and the 4U AS-4125GS-TNRT, as our overview of Supermicro servers for the RTX PRO 6000 Server Edition and our guide to 2U servers with four GPUs set out. For eight RTX PRO 4500 Server Edition cards, Supermicro's systems page for the card gives up to eight in the 3U SYS-322GA-NR and the 5U SYS-522GA-NRT, while Gigabyte writes generically of up to eight cards in 4U and four in 2U; the models are in our list of RTX PRO 4500 Server Edition compatible servers.
Shared storage and the network between nodes
Every node reads the same scene files, textures and caches, and every frame goes back to the same place, so the farm needs shared storage that all nodes mount under the same path. The renderers' own documents we read give no network figure. Our planning rule is 25 GbE per node: a 40 GB scene package takes about 13 seconds at the 3.125 GB/s line rate of 25 GbE and about 32 seconds at the 1.25 GB/s of 10 GbE, by our arithmetic before protocol overhead, and that wait repeats whenever a node loads a new job.
Check the network ports of each chassis in the quote. Supermicro's datasheet of the SYS-422GA-NRT lists two 10 GbE ports and an AIOM slot, while the SYS-422GL-NR has only a 1 GbE port for the BMC, so its data network comes from an added card. Our AI servers page lists 25, 100, 200 and 400G network cards among the components we size.
Power and heat per render node
A render job keeps the cards under load for hours, so plan the feed for the full node. Four RTX PRO 6000 Server Edition cards at 600 W draw 2.4 kW on their own. With two AMD EPYC 9355, our published estimate for a four-card node is about 3.4 kW at the wall, or about 2.7 kW with the cards capped at 450 W, and our guide to GPU server power on 16 A, 32 A and three-phase feeds plans 5.89 kW for a 230 V 32 A feed at 80 %. By our arithmetic, one such feed carries one four-card node, and three nodes at about 10.2 kW belong on three-phase power. Eight RTX PRO 4500 Server Edition cards draw 1,320 W, with processors, memory, fans and conversion losses on top. A capped card renders more slowly, so the power level belongs in the quote, and the electrical power ends up as heat that the room has to remove.
Rendering at night on the VDI hosts
A firm that already runs virtual workstations can render on the same cards after hours. Our article on a GPU platform for engineering firms describes the schedule: CAD desktops on time-sliced vGPUs by day, and at night one render VM with a whole 96 GB card or several cards, which counts as one render machine for the renderer licence and takes one RTX vWS licence while it runs. Draining the queue and restarting the desktop pool before office hours is part of the queue manager's job. Our guide to an AI server for creative agencies shows the same day and night split with image and video models.
We supply the RTX PRO 6000 Server Edition and the RTX PRO 4500 Server Edition as cards or in servers built to order, assembled and tested before delivery. On request we pre-install the operating system, drivers, CUDA and a container runtime, with remote setup by our engineering partner Vixen.UNO; for cards alone you can request our current NVIDIA price list. Describe your frame volume and renderer, and we size the nodes and the feeds.
FAQ
How do I build a GPU render farm?
How many render nodes do I need?
Do I need a Redshift licence for every render node?
How many render node licences come with Octane?
Is Deadline 10 still supported?
RTX PRO 6000 or RTX PRO 4500 for a render node?
How much power does a GPU render node draw?
We supply render nodes with RTX PRO 6000 or RTX PRO 4500 Server Edition cards, built to order. Tell us the renderer, the queue manager you plan and the size of your heaviest scene, and our team will help. We reply within one business day.