- A deskside AI workstation takes up to four actively cooled cards: NVIDIA states that the 300 W RTX PRO 6000 Max-Q “enables up to four GPUs in a single system”, while the 600 W Workstation Edition stops at one or two per tower in the makers’ specifications
- The RTX PRO 6000 Server Edition, the L40S and the L4 are passive cards, and NVIDIA’s H200 page describes the H200 NVL as a dual-slot, air-cooled PCIe card; all four take their air from the fans of a server chassis
- Tower GPU servers add a BMC and 1+1 redundant power supplies but take fewer and smaller cards: Dell’s PowerEdge T560 takes two 300 W double-width cards, Supermicro’s SYS-741GE-TNRT up to four, without the H200 NVL or the RTX PRO 6000 Server Edition in its GPU list
- Lenovo’s 2U SR650a V4 takes two 600 W cards or four at 400 to 450 W; eight 600 W cards need a 3U or 4U chassis, mostly with PCIe switches, three-phase power and a server room or data centre
- A department can start on a workstation for development and tests; a service for the whole company, virtual machines with vGPU and models split over NVLink move to rack servers
Supplied by Eurokommerz: AI servers, built to order Request a configuration →
Which machine for which cards
Up to four GPUs with their own fans fit a deskside AI workstation: NVIDIA states that the RTX PRO 6000 Max-Q, a 300 W card with active cooling, “enables up to four GPUs in a single system”. 600 W server cards such as the RTX PRO 6000 Server Edition and the H200 NVL, and any build of more than four cards, need a rack-mounted AI server whose fans push air through them. A tower GPU server sits between the two, with server management and redundant power supplies in a deskside or rack-convertible chassis, for two to four cards of up to about 400 W. We build GPU workstations and rack servers to order with these cards. Send us the cards you plan and the room each machine will stand in, and we answer with the form factor, a configuration and a written quote within one business day.
The card count and the cooling the cards need decide first; noise, the power circuit, remote management through a BMC, warranty service and the room come next. Whether a team of 5 to 30 needs one shared GPU server or a workstation per person is a separate question with its own guide. The room itself, from circuits to BTU/h, is covered in our guide to a GPU server in an office, and rack feeds and cooling in our guide to GPU rack power and cooling.
Active and passive GPUs: which card goes in which chassis
NVIDIA lists the cooling of each card on its product pages, and that row decides the chassis. An active card has its own fan and moves its own air, so it works in a workstation case. A passive card has only a heat sink. NVIDIA’s H200 page describes the H200 NVL as “PCIe Dual-slot air-cooled” and gives it a maximum of “Up to 600W (configurable)” (page updated 27 August 2026, read 23 November 2026). Lenovo’s product guide for the RTX PRO 6000 Server Edition states: “The card is passively cooled and is capable of 600 W maximum board power.”
| CARD | COOLING | MAXIMUM POWER | CHASSIS |
|---|---|---|---|
| RTX PRO 6000 Workstation | double flow-through | 600 W | workstation, one or two per tower |
| RTX PRO 6000 Max-Q | active | 300 W | workstation, up to four |
| RTX PRO 5000 (48 or 72 GB) | active | 300 W | workstation or tower server |
| RTX PRO 6000 Server Edition | passive, or liquid | up to 600 W, configurable | rack server |
| H200 NVL | air-cooled, dual-slot | up to 600 W, configurable | rack server |
| L40S | passive | 350 W | rack or tower server |
| L4 | passive, low profile | 72 W | rack or tower server |
Cooling and power from NVIDIA’s product pages (RTX PRO 6000 Workstation, Max-Q and Server Edition, RTX PRO 5000, L40S, L4), read on 10 October 2026, and NVIDIA’s H200 page (updated 27 August 2026, read 23 November 2026); passive cooling of the Server Edition and the L4 from Lenovo Press LP2263 (updated 28 July 2026) and LP1717 (updated 15 September 2024). Chassis column from the makers’ documents cited in this article.
The Workstation Edition is the exception among the active cards. Its double flow-through cooler releases 600 W into the case, and the tower makers list one or two per machine; our guide to the four-card Max-Q workstation shows which towers take four Max-Q cards and which power supplies they need.
Virtualisation narrows the choice. NVIDIA’s list of GPUs supported by vGPU, updated on 2 October 2026, includes the L40S, the L4 and, of the three RTX PRO 6000 editions, only the Server Edition. Some actively cooled cards are on it as well, among them the RTX 6000 Ada and the RTX PRO 5000 Blackwell Workstation Edition 72 GB, added in vGPU 20.2 and listed for Red Hat KVM, not vSphere (vGPU 21.0 platform pages, 12 November 2026). Virtual machines with vGPU on the RTX PRO 6000 therefore mean the passive Server Edition, and with it a server.
GPU workstation: up to four active cards under a desk
A GPU workstation with four RTX PRO 6000 Max-Q holds 384 GB of GPU memory and runs on one 16 A circuit at 230 V of its own. It suits one team that develops and tests models and has no server room, and MIG lets several developers share the cards on Linux, once NVIDIA’s DisplayModeSelector has switched each card to compute mode, which turns its display outputs off.
Workstations offer server management only as an option, if at all. Lenovo’s specification of the ThinkStation PX (version 11.0, 13 May 2026, read 10 October 2026), which lists the RTX PRO 6000 Max-Q, names Intel vPro with AMT for system management and offers a BMC as a PCIe adapter. Intel’s AMT developer guide says its KVM feature “allows remote control of a client even if the OS isn’t running or if the system is asleep”; AMT is a management feature of Intel vPro client platforms, not a server BMC. The PX has one 1,850 W power supply and an optional second one; with both in team mode, Lenovo’s PSREF sheet of 9 October 2026 gives a configuration of up to 2,350 W. For a four-card build, ask the maker whether the configured load fits on one supply, because only then does the second one give redundancy.
Tower GPU server: BMC and redundant power in a deskside chassis
A tower server has the management of a rack server, with a BMC on its own network port and hot-plug power supplies, in a case that stands on the floor or converts to a rack. Dell’s technical guide for the PowerEdge T560 (Rev. A04, December 2024) gives “Up to 2 x double-width 300 W or 6 x single-width 75 W accelerators”, lists the A40 and L40 at 300 W and up to five L4, and supports “up to two AC power supplies with 1+1 redundancy”, managed through iDRAC9. HPE’s QuickSpecs describe the ProLiant Compute ML350 Gen12 as a “4U tower with rack conversion capability”, list the L40S and the L4, and require the redundant fan kit and the second CPU fan kit whenever a GPU is selected; management is iLO 7 with a dedicated 1 Gb port at the rear. Lenovo’s L4 product guide lists its ST650 V3 tower for up to eight L4, while its RTX PRO 6000 Server Edition guide marks the ST650 V3 as not supported.
Supermicro’s page for the SYS-741GE-TNRT lists the form factor as “Tower Rackmount”, “Up to 4 double-width GPUs” and “2x 2000W Redundant (1 + 1) Titanium Level (96%) power supplies”, with an optional rear fan kit “for passive GPU cooling”. Its GPU list includes the H100 NVL, which NVIDIA rates at 350 to 400 W, the L40S, the L4, the RTX PRO 4000, 4500 and 5000 Blackwell and the RTX PRO 6000 Blackwell Max-Q Workstation Edition, but neither the H200 NVL nor the RTX PRO 6000 Server Edition. None of the tower servers in these documents lists a 600 W passive card.
Tower servers are loud for an office. Dell declares the T560 at 4.4 to 8.6 B of sound power in operation at 25 °C across its configurations, notes that acoustic output is higher when a GPU card of 75 W or more is installed, and calls it “a tower server appropriate for attended data center environment”.
Rack GPU server: four to eight passive cards
Rack servers are built around the airflow passive cards need. Lenovo’s 2U ThinkSystem SR650a V4 takes “four 400W or two 600W double-wide GPUs, or eight single-wide GPUs” according to its product guide (updated 5 October 2026). Its GPU table allows four RTX PRO 6000 Server Edition cards only when they are capped at 450 W, two at 600 W, and two H200 NVL. The server has up to two hot-swap redundant power supplies of up to 3,200 W, and its XClarity Controller 3 BMC has a dedicated Ethernet port and supports IPMI 2.0, SNMP 3.0 and the Redfish REST API. The Lenovo figures show what a 2U chassis allows.
Eight 600 W cards need a 3U or 4U chassis, mostly with PCIe switches, four to eight power supplies and three-phase power, as our article on how many GPUs fit in one server works out per chassis. NVIDIA’s H200 page gives the H200 NVL a “2- or 4-way NVIDIA NVLink bridge” at 900 GB/s per GPU, so a model split across four cards exchanges data over NVLink instead of PCIe. With their declared noise and heat, these servers go in a server room or a data centre, as our office guide shows.
We build AI servers to order, from GPU workstations to 2U and 4U GPU chassis. Send us the depth of your rack, its power feed and the cooling in the room, and we check rack, power and airflow before we quote the server.
Remote management, redundant power and warranty service
A BMC lets the operations team power-cycle a server, open its console, update firmware and read temperatures, fan speeds and power draw over the network, independently of the operating system. Through Redfish or IPMI the same data reaches the monitoring system that watches the other servers, while a workstation that hangs at night needs someone at the desk unless it has AMT or an optional BMC.
Redundant supplies keep a server running when one supply or feed fails. Rack and tower servers offer 1+1 supplies; a workstation with two supplies is redundant only while its load fits on one.
Warranty service is set by the supply contract for each form factor. Ask who takes the warranty case for the GPUs, the chassis maker or the card maker, and how a failed card is replaced in a server that stays in production. Our guide on where to buy an AI server in Europe covers the order and the warranty case for each kind of supplier.
Rack server, tower or workstation: the three form factors compared
| FORM FACTOR | GPUS PER MACHINE | POWER SUPPLIES | MANAGEMENT | WHERE IT STANDS |
|---|---|---|---|---|
| Workstation | 4 Max-Q, or 1 to 2 600 W | one, optional second | AMT on Intel vPro, BMC as option | office, lab |
| Tower GPU server | 2 to 4 double-width up to 400 W, or up to 8 L4 | two, hot-plug | BMC with its own port | branch, small server room |
| 2U, e.g. SR650a V4 | 2 at 600 W, 4 at 400 to 450 W | two, redundant | BMC with its own port | server room, data centre |
| 3U or 4U rack server | 4 to 8 at 600 W | four to eight | BMC with its own port | data centre, three-phase feeds |
Lenovo ThinkStation PX specifications version 11.0 (13 May 2026); Dell PowerEdge T560 technical guide Rev. A04 and Supermicro SYS-741GE-TNRT page (1+1 redundancy); HPE ML350 Gen12 QuickSpecs a50006995enw; Lenovo Press LP1717 and LP2128; all read on 10 October 2026. 3U and 4U figures from our article on how many GPUs fit in one server.
Above four cards, and for any 600 W passive card, the choice is a rack server. Below that, the room decides: a workstation where people sit, a tower server where a branch office has a small server room but no rack, and a rack server wherever a rack with a suitable feed exists. Four RTX PRO 6000 Server Edition cards at their full 600 W need a chassis whose maker lists four at that power, such as a 3U or 4U GPU server, since the 2U SR650a V4 takes four only at 450 W; our list of servers compatible with the RTX PRO 6000 Server Edition gives the count per model, and our comparison of 2U and 4U servers for four GPUs weighs the two chassis.
From one department to the whole company: an example
This example is illustrative, not a sizing. A manufacturer with 1,200 staff starts its first AI project in the engineering department. The team builds and tests a document assistant on a workstation with four RTX PRO 6000 Max-Q. NVIDIA’s CUDA GPU list gives the Max-Q, the Workstation Edition and the Server Edition the same compute capability, 12.0, so the containers tested on the workstation run on the server cards; throughput changes with the power limit and the Server Edition’s lower memory bandwidth.
When the assistant goes to all staff, it moves to two rack servers with four RTX PRO 6000 Server Edition cards each, the inference node we build to order, managed through their BMCs like the rest of the server estate. With two servers, one keeps serving while the other is in maintenance. If the company later needs virtual GPU desktops for its designers, the Server Edition cards run vGPU; if it needs a model split across cards over NVLink, H200 NVL servers with four-way bridges join the rack.
| SCENARIO | FORM FACTOR | REASON |
|---|---|---|
| One team, development | workstation, 4 Max-Q | active cards, office circuit, MIG |
| Branch or lab, small models | tower server, L4 or L40S | BMC and 1+1 power without a rack |
| Virtual desktops or GPU VMs | rack server, Server Edition or L40S | both on NVIDIA’s vGPU list, BMC |
| Company-wide assistant | two rack servers, 4 to 8 cards each | BMC, redundancy, one in maintenance |
| Model split over NVLink | rack server, H200 NVL | NVLink bridges, 141 GB per card |
Cooling, vGPU and NVLink from NVIDIA’s product pages, including the H200 page; compute capability from NVIDIA’s CUDA GPUs page; tower limits from the makers’ documents above.
Outline your teams and models in the form below, and we reply within one business day with a configuration and quote.
Workstations and GPU servers we build to order
We build AI servers to order, from GPU workstations on Threadripper PRO or Xeon W platforms and short-depth servers for labs, pilots and branch sites to 2U and 4U GPU chassis. The servers come with redundant power supplies, out-of-band management through IPMI or a BMC and air or liquid cooling chosen by GPU count and site. The GPUs we supply for them include the RTX PRO 6000 Workstation Edition, Max-Q and Server Edition, the RTX PRO 5000, the H200 NVL, the L40S and the L4. Each server is assembled and tested before delivery and comes with manufacturer warranty on one EU contract and invoice. We supply servers from Supermicro, Gigabyte, ASUS, Dell, HPE, Lenovo and other makers per project. We check the rack, power and airflow before we quote, and the configuration and quote follow within one business day.
FAQ
Should I buy an AI workstation or an AI server?
Is a rack or a tower better for a GPU server?
What is a tower GPU server?
Workstation vs server for LLM inference: what is the difference?
What is a deskside AI server?
How many GPUs fit in a rack server for AI?
Send us the number of cards, the models you will run and the room or rack each machine goes into. We answer with the form factor, a configuration from workstation to 4U GPU server and a written quote within one business day.