A failed GPU in an HGX server: diagnosis, running on seven GPUs and the maker's service
Eurokommerz, Vienna, since 2006: Private AI/ML · IT Managed Services · Enterprise Training · AI Hardware & Software
- None of Supermicro, ASUS and Gigabyte publishes how a failed SXM GPU is replaced on its HGX servers; Supermicro's manual names a GPU node FRU, GPU-FRU-B300-6U-AC-NODE, and NVIDIA's DGX service manuals list no GPU part as customer-replaceable
- A failing GPU shows in the kernel log as an Xid, such as 79 for a GPU that has fallen off the bus or 48 for an uncorrectable ECC error, and NVIDIA's Fabric Manager guide says a GPU that fails to register loses its NVLink peer-to-peer capability
- On seven GPUs a layout that spreads one model over all eight stops; two copies over four GPUs each keep one copy running, and single-GPU replicas or MIG instances lose only one eighth
- ASUS's EU advance replacement terms state next-working-day delivery in EU countries and dispatch on the same working day for requests before noon; Gigabyte puts on-site service in a separate quotation, and its warranty sends GPUs to the terms of their original maker or the purchase order
- We do not service hardware on site: warranty and service come from the server maker, at the level configured in the quote, and are handled through us
Supplied by Eurokommerz: AI servers, built to order Request a configuration →
What happens when one GPU on an HGX board fails
When one of the eight GPUs on an HGX B200 or HGX B300 board fails, the repair is a job for the server maker's service. Supermicro, ASUS and Gigabyte do not publish whether they swap a single SXM module, the GPU tray or the whole baseboard; Supermicro's manual for the SYS-822GS-NB3RT names a GPU node as a field-replaceable unit, and NVIDIA's service manuals for the DGX B200 and DGX B300 list no GPU part among the components a customer may replace. Until the part is back, the server runs on seven GPUs or not at all, depending on how the workload was laid out.
That last point is decided before the fault, in the serving or training layout, and in the service level bought with the server. This guide follows a fault from the first log line to the maker's RMA route. The general terms of on-site contracts are in our guide to on-site service for GPU servers, and warranty periods with the seller's liability in GPU server warranty in the EU.
We supply HGX B300, HGX B200 and HGX H200 servers per project from Supermicro, ASUS, Gigabyte, HPE and Lenovo; warranty and service come from the server maker, at the level configured in the quote, and the claim is handled through us. For an order we need the end user's company, the installation site and the intended use, which the server maker and NVIDIA review before they confirm the project, as our guide to the end-user certificate for NVIDIA GPUs describes. Tell us the service level your operation needs and the site address, and we have it priced with the maker.
How a failed GPU shows on an HGX server
The first sign is usually a line with NVRM: Xid in the kernel log, carrying the PCI address of the GPU and a code. NVIDIA's Xid catalogue, as our Xid reference sets out from the copy of 4 November 2026, gives each code an immediate action:
- XID 79, a GPU that has fallen off the bus: restart the system, drain the node and report the issue to the system vendor.
- XID 48, an uncorrectable ECC error; if 63 or 64 follows, drain the node and reset the GPU. A row remapping failure confirmed by NVIDIA's field diagnostic meets NVIDIA's RMA criteria.
- XID 74, an NVLink error, which "may indicate a problem with the device at the remote end of the link", so read the logs of the other GPUs as well.
- XID 154 names the recovery action the driver now expects, such as Node Reboot Required, and
nvidia-smi -qshows the same value as the GPU Recovery Action.
The catalogue's applicability columns name the A100, H100, B100 and GB200, not the B200 or B300 by name, so read each code with that caveat. On an HGX board the NVLink side adds a second signal. NVIDIA's Fabric Manager guide states that on H100 and later a GPU that fails to register with the fabric "will lose its NVLink peer-to-peer capability", and that in some configurations CUDA initialisation fails with cudaErrorSystemNotReady while the fabric service is not running. A job that suddenly sees fewer peers, or errors in the Fabric Manager log (journalctl -u nvidia-fabricmanager), points at one GPU or its links.
Before anything is reset, collect the evidence the maker will ask for: the output of nvidia-bug-report.sh, the full kernel log, and the mapping of PCI address to serial number with nvidia-smi and --query-gpu=index,pci.bus_, as our guide to identifying a faulty GPU by bus ID, slot and serial shows. Then run dcgmi diag -r 3; the DCGM documentation, measured on Hopper systems, gives under 35 minutes with eight GPUs. NVIDIA calls its field diagnostic "usually required before an RMA can be started", and the system vendor says when and how to run it.
Which layouts keep running on seven GPUs
An HGX board joins its eight GPUs in one NVLink domain, and the layout of the work decides how much of it a single failure stops. The table is our reasoning for inference; GPU memory per NVIDIA's HGX page (180 GB per B200, 2.1 TB for eight B300, about 270 GB each).
| LAYOUT ON 8 GPUS | WITH ONE GPU OUT | MEMORY PER COPY |
|---|---|---|
| One model over 8 GPUs | stops until the GPU is back | B200 1,440 GB, B300 2.1 TB |
| Two copies over 4 GPUs each | one copy keeps serving | B200 720 GB, B300 about 1,080 GB |
| Four copies over 2 GPUs each | three copies keep serving | B200 360 GB, B300 about 540 GB |
| Eight single-GPU copies | seven keep serving | B200 180 GB, B300 about 270 GB |
| MIG, 7 instances per GPU | 49 of 56 instances remain | B200 1g.23gb, B300 1g.34gb |
our arithmetic and reasoning; per-GPU memory from NVIDIA's HGX page and MIG profiles from NVIDIA's MIG user guide (updated 4 November 2026), both as recorded on 27 November 2026.
The row that matters is the first. A model whose weights and cache need more than half the board has no fallback inside the server: on HGX B200 that is anything above 720 GB per copy, on HGX B300 above about 1,080 GB. For such a model the layout that survives a GPU fault is a second server, as our guides to high availability for LLM inference with two nodes and to one 8-GPU server or two 4-GPU servers explain. Where the model fits four GPUs, two copies of four give half the capacity during the repair, and the three GPUs beside the failed one can still run smaller models or MIG instances.
For training, a job across all eight GPUs stops at the fault and resumes from the last checkpoint, on seven GPUs where the framework and the parallel layout allow it, or on eight after the repair. That is one reason the checkpoint interval belongs in the plan, as our guide to storage for HGX servers works out.
What the maker replaces
NVIDIA's service manuals are the clearest published reference for the HGX platform. The DGX B200 manual (dated 13 September 2026) lists power supplies, fans, drives, the storage network card, DIMMs and similar parts as customer-replaceable; the DGX B300 manual (30 April 2026) adds the E1.S drives, the BlueField-3 I/O bay and the DC-SCM module. Neither lists a GPU, the GPU tray or the baseboard. The B300 manual notes that "The back of the system allows access to the GPU tray, motherboard tray, and power supplies" and sends the reader to NVIDIA Enterprise Support "for replacement instructions and guidance for specific components". By that reference the GPU side of an HGX system is serviced as an assembly by the maker's service, and not by the customer.
Supermicro's online manual for the SYS-822GS-NB3RT lists "PIO-822GS-NB3RT-NODE" for the motherboard and "GPU-FRU-B300-6U-AC-NODE" as the GPU node FRU. Whether a single SXM module is ever swapped in the field, or always the node, is not stated. ASUS and Gigabyte publish no part split for their HGX servers on the pages we read. Ask the maker in writing, through us, which unit its technician or its RMA replaces for a GPU fault, and how long that unit takes to arrive.
ASUS server RMA and advance replacement in Europe
ASUS's RMA service page for servers names two routes. The Onsite Service is offered "for select server products under warranty", and an Advance Replacement Service sends a part before the faulty one returns. The page's table gives server systems a standard warranty of 3, 2 or 1 year for labour and parts, depending on the product and the invoice, and stand-alone components one year; "If the invoice specifies different warranty terms, those apply". An RMA needs proof of purchase, the invoice number, the model, the serial number and a fault description. If ASUS has no replacement part within 30 days, it may repair the unit or substitute an equivalent or refurbished part.
The European terms of the Advance Replacement Service are more specific. They apply "to Europe and some Middle East and African countries"; for servers they cover "electronic parts and parts which might influence the system function & operating". ASUS states next-working-day delivery for EU countries only, sends the part on the same working day if the request arrives before noon, and pays the freight in both directions. The defective part goes back within 14 days, and ASUS inspects it within 3 working days. The terms name neither GPUs nor GPU trays, and on-site work is not part of them. Our review of the ASUS XA NB3I-E12 covers the HGX B300 model itself.
Gigabyte Enterprise warranty and RMA
Gigabyte's warranty page for enterprise products gives servers, barebones and workstations "a three (3) year limited warranty ... under normal operating conditions". Direct-liquid-cooled barebones also carry three years, and "Manifolds and Cold Plates manufactured by GIGABYTE have a base warranty period of one (1) year". For an HGX server one clause decides more than the period. CPUs, GPUs, memory and storage from other makers are "subject to the warranty terms of the original manufacturer or the specific Purchase Order (PO)". Gigabyte lists the G894-SD3-AAX7 under its ordering number as a barebone with the NVIDIA module, so by our reading the warranty for the GPU board has to be written into the purchase order.
The first contact is the company that sold the product; Gigabyte answers directly only for products bought from it. On-site service and extended warranty "require a separate quotation and a formal written agreement". Gigabyte publishes no advance replacement or turnaround time on that page. The HGX models are described in our article on Gigabyte G894 servers for HGX B200 and B300.
Supermicro on-site service for HGX servers
Supermicro's document "Onsite Service" (March 2026) lists Bronze with "3 Business Days" and no field engineer, Silver with "Next Business Day", Gold with "4-hour Restore" and Mission Critical as "SOW Based". "To qualify for service, your purchase must consist of a complete Supermicro server." The clock starts "when the issue is determined to be a hardware issue, and the defective part is identified", and coverage beyond three years "does depend on the life cycles of the particular systems". Supermicro's European eStore sells Bronze and Silver, lists Austria, Germany and Switzerland as covered in full for both, staffs its help desk Monday to Friday from 9:00 to 17:00 local time, and notes "On-site service overrides Warranty". Supermicro describes its SYS-822GS-NB3RT with the words "(onsite service required)", as our review of the SYS-822GS-NB3RT quotes.
| MAKER | WARRANTY AS PRINTED | PART REPLACEMENT | ON-SITE |
|---|---|---|---|
| Supermicro | GPU systems: 3 years labour, 1 year parts, 1 year advance cross-ship | advance cross-ship; GPU node FRU named in the manual | Bronze, Silver, Gold, Mission Critical; EU eStore sells Bronze and Silver |
| ASUS | server systems 3, 2 or 1 year, by product and invoice | Advance Replacement, next working day in EU countries | Onsite Service for select server products |
| Gigabyte | servers 3 years limited; GPUs and other third-party parts by their maker or the PO | not published | separate quotation and written agreement |
Supermicro "Onsite Service" (March 2026), EU eStore add-on service page and Limited Warranty page (as in our warranty guide); ASUS RMA service page for servers and EU Advance Replacement terms; GIGABYTE Enterprise warranty page (©2026); read 27 November 2026 unless stated.
What the quote for an HGX server should state about service
- The warranty holder and period per component, the GPU board included, with labour and parts as separate terms.
- The on-site level, if one is bought, with its response time as the maker defines it, the country coverage for the installation site and the help-desk hours.
- The replacement unit for a GPU fault (module, tray or node) and where it is sent from, answered by the maker in writing.
- The diagnostics the maker expects before an RMA, so that your team can collect them without remote access the security policy forbids.
- The spare strategy: a second server, or a layout that keeps half the board serving.
Your data-centre staff or colocation provider rack the server and give the maker's technician access; we do not work on the hardware on site. On request we pre-install the operating system, drivers, CUDA and a container runtime, with remote setup by our engineering partner Vixen.UNO. The three makers' HGX models are compared in our comparison of HGX B200 and B300 servers from Supermicro, ASUS and Gigabyte. Ask us for the service options of the model you are considering, and the written quote lists the maker's terms for each.
FAQ
What happens if one GPU fails on an HGX B200 server?
Can a single SXM GPU be replaced on an HGX board?
Does ASUS offer on-site service for servers in Europe?
How does a Gigabyte server RMA work?
Is an HGX baseboard replaced as a whole?