Power cords and PDUs for HGX B200 and B300 servers: inlets, outlets and A/B feeds

Eurokommerz, Vienna, since 2006: Private AI/ML · IT Managed Services · Enterprise Training · AI Hardware & Software

IN BRIEF
  • An HGX server takes at least one power cord per supply: six supplies on Supermicro's 8U models with 6,600 W supplies, six or ten on ASUS, twelve on Gigabyte's 8U models
  • Gigabyte states that its 3,000 W supplies require a C19 cord and that cords are not included; it rates the input at 14.9 A from 220 to 240 V
  • Supermicro and ASUS print neither the inlet type nor the input current of their supplies; a 6,500 W output at 230 V is about 28 A before losses by our arithmetic, more than one 16 A C19 connection carries
  • With A and B feeds, each side of an N+N server takes half of its supplies and their cords, and each feed has to carry the whole server; Supermicro prints 15 kW at full load for its 8U HGX B300 node
  • NVIDIA's DGX B200 user guide gives no UPS requirement; by our arithmetic a UPS for one 15 kW server at 80 per cent load is about 19 kW, three-phase, with runtime for a clean shutdown

Supplied by Eurokommerz: HGX B200 servers  Request a price →

How an HGX server connects to the rack PDU

An HGX B200 or HGX B300 server connects to the rack with at least one cord per power supply: six supplies on Supermicro's 8U SYS-822GS-NBRT and SYS-822GS-NB3RT, each rated 6,600 W, six on the ASUS ESC NB8-E11, ten on the ASUS XA NB3I-E12 and twelve on Gigabyte's 8U G893 and G894 models. Gigabyte names the cord, a C19, and says the cords are not included; Supermicro and ASUS print no inlet type or input current, so the cord type is settled per order and belongs in the quote.

The kilowatts of these servers are covered in our guide to HGX B200 power consumption and cooling, which this article does not repeat. Here the subject is the physical chain: inlet, cord, PDU outlet, feed and UPS.

We supply HGX B200 servers and HGX B300 servers from Supermicro, ASUS, Gigabyte, HPE and Lenovo per project, with the power supplies and cords chosen for the rack. For an order we need the end user's company, the installation site and the intended use; the server maker and NVIDIA review the project before they confirm it, as our guide to the end-user certificate for NVIDIA GPUs explains. Send us the PDU model, its outlet type and the feeds at the rack, and we reply with the cords and supplies that fit them.

Supplies, cords and inlets per HGX server model

MODELSUPPLIESMODEINLET, CORDINPUT PER SUPPLY
Supermicro SYS-822GS-NB3RT6 × 6,600 W3+3not printednot printed
Supermicro SYS-422GS-NB3RT-LCC4 × 6,600 W2+2not printednot printed
ASUS ESC NB8-E11 (B200)6 × 3,000 W5+1not printednot printed
ASUS XA NB3I-E12 (B300)10 × 3,200 W5+5not printednot printed
Gigabyte G893 / G894, 8U12 × 3,000 W6+6C19, cords not included14.9 A at 220 to 240 V
Gigabyte G4L3-SD1-LAX58 × 3,000 W4+4C19, cords not includedas the 8U models

Supermicro's product pages and quick reference guide QRG-2867 (©2025), ASUS datasheets for the ESC NB8-E11 (29 May 2025) and XA NB3I-E12 (19 September 2025), Gigabyte's product pages; read 27 November 2026. The AMD model AS-8126GS-NB3RT and the B200 model SYS-822GS-NBRT have the same six supplies as the SYS-822GS-NB3RT; Gigabyte's G894-SD3-AAX7 page lists twelve redundant supplies without writing 6+6.

Gigabyte's pages are the only ones of the three makers that answer the cord question. "The system PSU requires a C19 power cord", and "Power cords are not included with server packages". The same pages give the input current as 14.2 A at 115 to 127 V, 15.8 A at 200 to 220 V and 14.9 A at 220 to 240 V. Under IEC 60320 a C19 connection is rated at 16 A, so all three values fit one C19 outlet, and twelve supplies need twelve such outlets. At 115 to 127 V the same supply delivers only 1,450 W instead of 2,900 to 3,002.4 W, so these servers are planned on 200 to 240 V. The ASUS datasheets state that the power configuration differs "by region", and Supermicro's model pages, its manual overview and its quick reference guide name no inlet; its power-supply matrix returned no entry for these models when we read it.

The 6,600 W supply in Supermicro's 8U servers

Supermicro's 6,600 W Titanium supply delivers 6,500 W at 230 to 238.9 V and 5,900 W at 200 to 207.9 V. At 230 V, 6,500 W of output is about 28 A by our arithmetic, before conversion losses, and about 30 A of input current at the 95.33 per cent full-load efficiency of the 80 PLUS report quoted in our review of the Supermicro SYS-822GS-NB3RT. That is more than the 16 A of one C19 connection. The review reads the report's input rating "16-15 x 2" as two AC inputs of up to 16 A per supply; Supermicro does not confirm that on its pages. Do not order PDUs or cords for these servers until the quote names the connector and the number of inputs per supply.

For comparison, NVIDIA documents its own systems closely; we do not supply DGX systems, but their guides are a useful reference. The DGX B200 user guide lists six 3.3 kW supplies with "C19/C20" connections, a cord rated "250VAC, 20A", "3,300 W @ 200-240 V, 16 A" per supply, and the instruction to "only use the NVIDIA-provided power cords"; the same guide states that the system only boots if at least three of its supplies are operational. The DGX B300 service manual (30 April 2026) states that "a separate AC cord is required for each power supply" for its twelve supplies, and both service manuals describe twist-locking power cords that come with the system.

Outlets per side for A and B feeds

An N+N server is split over two feeds with half of its supplies on each, so that one feed carries the server alone when the other fails. A 5+1 server cannot be split this way. With three of its six supplies on each feed, a lost feed leaves three supplies where the mode counts on five, by our count.

MODELSUPPLIESPER FEEDN SUPPLIES, RATED
Supermicro 8U, 3+36319.5 kW at 230 V
Supermicro 4U liquid, 2+24213.2 kW nominal
ASUS XA NB3I-E12, 5+510516 kW nominal
Gigabyte 8U, 6+612618 kW at 220 to 240 V
ASUS ESC NB8-E11, 5+16no A/B split15 kW nominal

our arithmetic from the makers' supply counts and ratings above; Supermicro at 6,500 W per supply at 230 V, Gigabyte at 3,002.4 W per supply at 220 to 240 V, ASUS at the nominal rating because no voltage table is printed. Supermicro's supplies may need two cords each, see above.

The last column is supply capacity, not what the server draws. For the draw, Supermicro's SRS-48UAC-B300SX rack page, read 27 November 2026, prints "15kW (full load power draw)" for each SYS-822GS-NB3RT node, the only full-load figure for an OEM HGX server we have found. NVIDIA rates its DGX B200 at 14.3 kW maximum. Each feed, each PDU and each UPS on an A/B pair has to carry that full figure.

The PDU in our guide to GPU server power on 16 A, 32 A and three-phase feeds, a 400 V 32 A three-phase model with an IEC 60309 plug and six C19 outlets, shows how quickly outlets run out. A Gigabyte 8U server with six cords per side fills one such PDU on each side completely. Spread over three phases that is two cords per phase, 29.8 A at the nameplate 14.9 A each, below the 32 A of the phase by our arithmetic; the server's real draw is shared over all twelve supplies until one side fails. A second server needs a second pair of PDUs. How 3+3, 5+5 and 6+6 behave when a supply or a feed fails is explained in PSU redundancy in GPU servers.

Three-phase rack PDUs at 400 V and 415 V

Planned at 80 per cent, one 400 V 32 A three-phase feed carries 17.74 kW, enough for one server at Supermicro's 15 kW per side, and two servers need two such feeds per side. The makers' own rack designs use larger PDUs. Supermicro's SuperCluster B300 datasheet lists "415V/60A 3Ph" PDUs, 38 of them for twenty air-cooled racks; Gigabyte's AI-AC-POD for HGX B300 lists four PDUs per rack with "Input: 415 V, 63 A, 3-phase", and its liquid-cooled AI-DLC-Rack six with "415 V, 100 A, 3-phase". At 415 V and 63 A a three-phase PDU is rated at about 45.3 kVA by our arithmetic, so Gigabyte's two PDUs per side give about 90.6 kVA for a rack of up to 70 kW. These are rack designs for four servers, described in our article on the makers' HGX B300 racks; our feed figures use the 400 V three-phase supply of European sites, so the PDU is specified for the local voltage.

NVIDIA's data-centre guide for the DGX H100, quoted in our PSU redundancy article, adds a rule that applies to any of these servers: "The power draw across the phases of a three-phase circuit should be as balanced as possible." With six, ten or twelve cords, spread them evenly over L1, L2 and L3 on each side.

A UPS for one 14 to 15 kW server

NVIDIA's DGX B200 user guide gives no UPS requirement, and the makers' pages we read give none either. Sizing therefore follows the method of our guide to a UPS for a GPU server, written for PCIe servers: the full-load power divided by 0.8, so that the UPS runs at no more than 80 per cent of its rating. One server at Supermicro's 15 kW comes to about 19 kW of UPS capacity by our arithmetic, a three-phase unit, and with A and B feeds each side's UPS carries the whole server. The runtime only has to cover a clean shutdown of the inference service or a checkpoint of the training job; a longer outage is a generator question.

Rack depth and room for the cords

The cords need room inside the rack as well, so the rack depth counts. Supermicro's 8U servers are 950 mm deep, Gigabyte's 8U models 923 mm, the ASUS ESC NB8-E11 885 mm and the ASUS XA NB3I-E12 945 mm. Supermicro's own HGX B300 rack is 1200 mm deep on its rack page and 1400 mm in its cluster datasheet; in a 1200 mm rack a 950 mm chassis leaves 250 mm by our subtraction for rails, the bend of the cords and any vertical PDUs. Our site survey for GPU servers lists the measurements, and preparing a server room for a GPU server the order of the work.

Capping the GPUs lowers the draw but not the outlets or breakers a server needs to boot at full power; that trade-off is in power capping for HGX B200 and B300 servers.

What to put in the enquiry

  1. The voltage measured at the PDU outlet and the breaker rating of each feed.
  2. The PDU model, its outlet types and the free outlets on each side.
  3. Whether the rack has A and B feeds and separate UPS units.
  4. The usable rack depth behind the front rails.
  5. The end user's company, the installation site and the intended use.

Your data-centre staff or colocation provider rack and connect the server; we do not work on site. Write to us with these five points, and the quote names the supplies, the cord type and the number of cords per server.

FAQ

Which power cord does an HGX B200 server need?
One cord per power supply, and the type depends on the maker. Gigabyte's 8U HGX B200 servers have twelve 3,000 W supplies that each require a C19 cord, not included. Supermicro and ASUS print no inlet type; the quote has to name it.
What power cord does a 6,600 W PSU use?
Supermicro does not print the inlet of its 6,600 W supply. By our arithmetic 6,500 W of output at 230 V means about 28 A before losses, more than one 16 A C19 connection carries; our Supermicro review reads the supply's 80 PLUS report as two 16 A inputs, which Supermicro has not confirmed.
How many PDU outlets does an HGX B300 server need?
At least one per supply: six on Supermicro's SYS-822GS-NB3RT, ten on the ASUS XA NB3I-E12, twelve on Gigabyte's G894-SD3-AAX7; Supermicro's 6,600 W supply may need two, which the quote has to confirm. With A and B feeds, half of them on each side.
Do HGX servers use C19 or C20?
Gigabyte's supplies require a C19 cord, and NVIDIA lists "C19/C20" connections for its DGX B200; C19 is the 16 A connector of IEC 60320 that rack PDUs offer as outlets. For Supermicro and ASUS the maker confirms the connector per order.
Does an HGX server need three-phase power?
By our arithmetic yes: a server in the 14 to 15 kW class exceeds the 5.89 kW that a 230 V 32 A single-phase feed carries at 80 per cent, and one 400 V 32 A three-phase feed per side carries 17.74 kW.
What UPS does an HGX B300 server need?
NVIDIA and the makers state no UPS requirement. For one server at Supermicro's 15 kW full-load figure, a three-phase UPS of about 19 kW with runtime for a clean shutdown, by our arithmetic; with A and B feeds, one per side.

We supply HGX B200 and HGX B300 servers from Supermicro, ASUS, Gigabyte, Dell, HPE and Lenovo per project, with supplies and cords chosen for your PDUs. Send us the PDU model, the feeds, the end user, the site and the intended use. We reply within one business day.

Request a price
Talk to an expert

We reply within one business day

We use your details only to answer your enquiry; see our privacy policy.

request@eurokommerz.at
Jordangasse 7, 1010 Vienna